How to remember ITTOs of Integration management? ITTO is an acronym that stands for Inputs, Tools and Techniques, and Outputs.
Do we need memorize ITTOs for all the 49 project management processes included in PMBOK Guide, Sixth Edition? I believe it’s a never ending debate, ever since the PMBOK Guide and PMP certification examination came into existence.
Should you memorize them all? Why not? If you can memorize ITTOs for all the 49 processes, please go ahead by all means. If you can memorize them all, it is NOT necessary for you to read the rest of this article. This article is written with an aim to help those candidates who cannot memorize all the ITTOs.
Trying to memorize all of the inputs, tools, techniques, and outputs (ITTOs) for the PMP® and CAPM® exams can be overwhelming. There are lots of them. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) 6th Edition was released September 2017. The new PMBOK ® Guide 6th edition contains 978 pages, including the Agile Practice Guide (186 pages). PMP ITTO.pdf - Free download as PDF File (.pdf), Text File (.txt) or view presentation slides online. How do I memorize ITTO for the PMP test? (Before we begin, mastering ITTO means memorizing the 47 PMP processes of PMBOK 5.) Mastering ITTO – A 5 Minute Video. Among other things, I provide private Skype consulting on passing the PMP test. For recent clients, they keep asking “how to master ITTO”. Understanding the ITTOs is vital to pass the PMP Exam. Atleast 40% of the PMP Exam questions (roughly 80 out of 200), can be answered correctly if you have a solid understanding of the Inputs, Tools & Techniques, and Outputs of the Processes and their interactions.
To be honest, there was a possibility to memorize ITTOs until PMBOK Guide Fourth Edition or even until PMBOK Guide Fifth Edition. I personally feel, PMBOK Guide Sixth Edition has certainly made it near impossible to memorize ITTOs. The sheer number of inputs, tools and techniques and outputs for each process would certainly be beyond normal humans’ capability to memorize them.
![Pmp Pmp](https://i.pinimg.com/736x/15/87/32/1587329beac63421482b2b662f3de575.jpg)
The only way out, in my opinion, is to understand what is happening in each process. Then, try to use logic, common sense and your project management experience to figure out what could be the appropriate ITTOs for a given process.
In this attempt, I found the approach of drawing the process flow of each knowledge area helps very much in understanding and remembering the Inputs and Outputs.
Free monopoly spongebob edition full crack idm. I have given the process flow for Project Integration Management below. I have included ONLY the major inputs and outputs, so that it is easier to understand rather than complicating it too much. Please note that it does NOT include ALL inputs and outputs. I have included only those inputs and outputs, which I felt as important.
My advice to you is to draw the above process flow diagram yourself. You might choose to include more inputs and outputs; or even some of the tools and techniques. It would help your mind to map the inputs, tools and techniques and outputs to the processes; and you would not forget it.
This may not be an exhaustive list. But, I am just giving you some of the tips which I think would be useful to you.
Pmp Itto Excel
- Organizational Process Assets is an input to all the 7 processes of Project Integration Management.
- Expert Judgment is a Tool & Technique used in all the 7 processes of Project Integration Management.
- Enterprise Environmental Factors is an input to 6 processes of Project Integration Management (the only exception is Close Project or Phase process).
- Once Project Management Plan is developed in 4.2 Develop Project Management Plan process, it becomes an input to all the remaining 47 processes in this knowledge area. Only Develop Project Charter process does not involve project management plan, neither as an input nor as an output.
- Change requests is an output of 24 processes; but it is an input only to one process.
- Change requests can be an input only to Perform Integrated Change Control. It means, wherever a change request is generated, it will be sent to Perform Integrated Change Control process for further review.
- Approved change requests can be an output of only Perform Integrated Change Control process. None of the other 48 processes can have Approved change requests as an output. This is obvious because all change requests generated in the project have to be reviewed only through the Perform Integrated Change Control process. So, only this process can approve change requests.
- For all Monitoring & Controlling processes, change requests is an output; the only exception is Perform Integrated Change Control. In this process, change requests is an input and Approved change requests is an output.
What is your approach to remember ITTOs in Project Integration Management? Do you think the above approach is good? Do you have any other tips you want me to include in the above list?
Would you be interested in similar process flow charts for other knowledge areas too?
Share your opinions, comments and criticism in the comments below.
![Itto Pmp Chart Itto Pmp Chart](https://www.examspm.com/wp-content/uploads/2018/05/Project_Resource_Management.png)
Pmp Itto Chart Pmbok 6
- Yet another PMP Success Story - October 21, 2019
- Project Management Using Microsoft Excel - September 10, 2019
- PMI-RMP Course by uCertify – Is it for You? - August 3, 2019